Turnkey detergent filling and packing line delivered to an Egyptian chemical producer

In March 2026 we delivered a complete multi-level line for liquid detergents to an Egyptian chemical producer, covering filling, capping, accumulation and palletizing.

Complete packaging line installed by Al Sakr Top Group: bottle turntable, liquid filler, capper and conveyor

What the line includes

The line has four stages from one supplier. An anti-corrosion liquid filler doses the product and a rotary capping station closes each container. Buffer accumulation conveyors decouple the machines from each other, and an end-of-line palletizing cell stacks the finished cases.

Filling corrosive, foaming products

Detergents and industrial chemicals are corrosive and many grades foam, so the filler uses corrosion-proof dosing and anti-foam nozzles. The filler platform handles containers from 50 ml to 20 L with ±0.25% to ±0.5% accuracy, and its product-contact parts are AISI 316L, PTFE and Viton.

Capping head tightening a red cap on a blue jerrycanFilling and capping machines with conveyor installed in a client factory hall

Capping and accumulation

The rotary capper applies 0.5 to 8.0 N·m of torque through servo or magnetic clutch control. Between stations, buffer accumulation tables hold 1 to 15 minutes of production across 2 to 12 lanes. Zero-pressure optical sensors stop containers from pushing against each other while they wait.

End of line

The palletizing cell handles up to 12 cases per minute, with picks up to 50 kg and pallets up to 2,400 mm high. It works inside optoelectronic light curtains and interlocked fencing.

How the line was delivered

The project followed our standard delivery sequence. We started with a consultation and needs assessment, then produced the 3D layout and electrical engineering. The machines were fabricated in house and passed Factory Acceptance Testing with the customer's containers, and our crews then installed the line and ran Site Acceptance Testing at production speed.

Complete turnkey lines usually take 8 to 14 weeks from approved 3D layout to commissioning. They come with operator training and a 12-month mechanical and electrical warranty.